Savannah River Site
Citizens Advisory Board
Recommendation 228
President’s FY 07 SRS Budget Shortfall
Background
At any given time SRS is
working on various phases of three fiscal year (FY) budgets concurrently.
For example, in October
2005 while the FY 2006 budget is being executed, internal deliberations are
underway for the FY 2007 budget and the requirements for the 2008 budget are
being assembled.
This “annual” budget
process is how the DOE budget process operates.
For the Savannah River Site the budget process follows four steps: 1)
site requirement development; 2) internal DOE and Office of Management and
Budget deliberations; 3) congressional action; and 4) execution.
Generally, the requirements
development phase starts 2½ years prior to the start of the fiscal year. During this phase, the many and varied
environmental and compliance requirements are distilled into a one year funding
request. The internal deliberations
phase starts around April of each year and lasts about 10 months. DOE’s Environmental
Management Office (EM) compares the budget requests across the complex to the
budget targets issued by OMB and identifies issues that need to be resolved and
holds an Internal Review Board meeting to resolve issues and work towards an
acceptable EM budget submission to DOE-Headquarters. Once the issues have been resolved the budget
is submitted to DOE’s Chief Financial Officer for
final management decisions in early June.
At this point the DOE budget becomes part of the President's budget. For the next several months, the various
congressional committees with jurisdiction over EM’s program hold hearings and
modify the budget as it makes its way through the legislative process. The committees usually conference in early
fall and EM is appropriated funding around the beginning of the fiscal
year. Once funds are appropriated,
DOE-HQ provides funding to the sites and the task of executing the budget
begins (Ref 1).
The President's budget is
generally viewed as a detailed outline of the Administration's policy and
funding priorities, as well as a presentation of the economic outlook for the
coming fiscal year. The President's budget serves as a "starting
point" for the Congress to consider. Congress is under no obligation to adopt
all or any of the President's budget and often makes
significant changes.
The
President’s FY 07 budget for SRS is presented below compared to other
comparable DOE sites (Ref 2).
|
Site
|
|
|
|
FY 2006 Adjusted Appropriations
|
FY 2007 Congressional Request
|
% Change, FY07 vs FY06
|
$ Change
|
|
Idaho
|
538,083
|
519, 604
|
-3.4
|
-18,479
|
|
Oak Ridge
|
485,869
|
471,335
|
-3.0
|
-14,534
|
|
Hanford
|
1,665,471
|
1,803,686
|
+6.0
|
+138,215
|
|
Savannah River
|
1,178,720
|
1,084,394
|
-8.0
|
-94,326
|
|
|
|
The
decrease according to DOE for the Savannah River Site primarily reflects
completion of the deactivation of F-Canyon and associated facilities; and
completion of operations in the F-Area plutonium storage facility and the
consolidation in one building in K-Area. It also reflects phased completion of transuranic waste activities and lower waste stream volumes
and reductions in facility D&D activities to accommodate higher priority
activity. Some of the major areas
covered by the budget include the following: $24M for ongoing design and
construction of a 3013 Container Surveillance Capability in Building 105-K; and
$37.5M to continue design to address seismic and other technical issues and
$25.7M to begin construction of the Salt Waste Processing Facility.
Comment
At first glance at the
President’s FY 07 budget, the disparity between SRS and the other major DOE
sites is alarming. The SRS Citizens
Advisory Board (CAB) has major concerns about funding for other programs such
as the Historic Preservation issues, SREL, and operational funding for
HLW/TRU/LLW operations. Also, the SRS
CAB questions if the SWPF funding is adequate to meet the needs of this
facility. Since the President must
ultimately approve all future bills they propose, Congress is often reluctant
to completely ignore the priorities of the President's budget; therefore, the
SRS CAB has major misgivings about the $95 million shortfall in the FY 07
budget.
Recommendation
The SRS CAB is very
concerned that the President's budget for FY07, as submitted to Congress, will
not be sufficient to meet the goals for accelerated clean up of the Savannah
River Site. Therefore the SRS CAB recommends the following:
1.
The SRS CAB until
2 years ago was given the opportunity to be part of the early budget
process. The SRS CAB requests that DOE
return to that previous practice.
2.
By May 22, 2006,
DOE-SR present to the SRS CAB how the President’s FY07 Budget will affect or
impact accelerated cleanup goals; identify potential impacts to current
workforce levels (operational, technical and management); and provide a list of
EM programs impacted, especially those committed to in the FFA.
3.
DOE-HQ request
appropriate Congressional actions to provide SRS FY07 funding levels to rectify
any shortcomings identified in #2 above.
4.
By May 22, 2006,
DOE-SR present to SRS CAB potential secondary funding sources to offset the FY
07 shortfall and identify the sources and related activities that could be
accomplished.
References
1.
Citizens Advisory
Board Recommendation No. 149 (adopted January 15, 2002), “Stakeholder Input to
SRS Budget Process."
2.
U. S. DOE Office
of Environmental Management, FY 07 Budget Rollout,
www.em.doe.gov/Rispoli_07_EM_Rollout.pdf.
Agency Responses