Savannah River Site

Footprint Reduction Strategy

From 2009 - 2011

  • Yellow Accelerated
  • Blue Completion by 2011

Goals

  • Reduce operational footprint over 50% by 2011
SRS ARRA Map

M Area

  • Complete area closure
  • Small Arms Training Area remediation

B Area

  • 710 1B building facility demolition
  • Decommission of Heavy Water Components Test Reactor (HWCTR)
  • Waste storage area closure

E Area

  • 5,000 m3 transuranic waste shipped or ready to be shipped by 2012
  • 5 low-level waste trenches closure

F and N Areas

  • Ship 16,000 drums of depleted uranium oxide

D Area

  • Complete area closure

K Area

  • Cooling tower D&D

P and R Areas

  • Decommission P and R reactors
  • Close P and R ash basins
  • Complete remedial actions at P and R units
M Area B Area D Area E Area F Area F Area K Area P Area R Area
Department of Energy Savannah River Site Savannah River Nuclear Solutions Savannah River Remediation